Can specific start/end dates (1/2 month) be available when adding Shemesh charges to contract?
0
votes
809
views
asked
Dec 22, 2015
in
Tuition and Fundraising
by
Rochel
Right now, it is by month and if student gets different services within 1 month we cannot split it by date, but need to create 2 charges for that same month.
Thank you.
1 Answer
answered
Dec 22, 2015
by
Admin
selected
Dec 22, 2015
by
Pinkus
Best answer
This sounds like a specific question in the way you enter something. As this is a general forum nobody here knows what Shemesh Charges means and what you are trying to accomplish. Such type of questions are best handled by calling in to tech support.
commented
Dec 22, 2015
by
Rochel
I did ask tech support and was told to write in question in this forum - ?????
commented
Dec 22, 2015
by
Admin
So it seems like the feature you want is not available. You would need to generalize more the question in order for development to figure out what feature you are looking for so they can decide if they want to add it.
commented
Dec 22, 2015
by
Rochel
creating 2 charges in 1 month is ok - but does not allow for the correct start/end dates for the charges - it just looks like 2 charges for 1 month...I would like to choose the dates i.e.
start -- 12/1/2015 end 12/15/2015 charge 200.
start -- 12/16/2015 end 12/30/2015 charge 100.
Thank you.
commented
Dec 22, 2015
by
Admin
The due date in the charge will be the same as the start date. So in the above case you should get a different due date in the charge.
commented
Dec 22, 2015
by
Rochel
What I gave the example of is what I would LIKE to be able to do - and due date same as start date is fine, but JL does not allow for a mid-month START date - it does not put the charge in CHARGES tab - so, again, it just allows the following:
start 12/1/2015 end 12/15/2015 - good
for the 2nd 1/2 of month it does not allow to have start date middle of month so I need to just do:
start 12/1/2015 end 12/30/2015 -- not good!
commented
Dec 22, 2015
by
Admin
The charge needs to be set to yearly not monthly. As its a one time charge.
commented
Dec 22, 2015
by
Rochel
Thank you - it worked!
commented
Dec 22, 2015
by
Admin
Great. Please click on the check box to mark this completed.
All categories
How To
(704)
Minor Enhancements
(506)
Tuition and Fundraising
(261)
Tuition
(184)
Fundraising
(61)
Reports
(107)
New Feature Requests
(643)
Support Questions
(267)
School Administrators
(56)
Fundraisers
(62)
Off-Topic
(85)
New Feature
(202)
Let's Welcome our New Members
...